Talk to an Expert
Talk to an Expert ✆ +91 945 945 6700
Accounting Glossary · Industry

Percentage of Completion Method (POCM)

Percentage of Completion Method (POCM): Definition

The Percentage of Completion Method (POCM) recognises revenue and profit on a long project in step with how much of the work is done, rather than only when it finishes. Revenue and costs flow into the profit and loss account each period based on the stage of completion. It matters because it matches income to effort, avoiding lumpy results on multi-year construction and project contracts.

What Is the Percentage of Completion Method (POCM)?

For a contract that runs across several years, waiting until handover to book all the revenue would leave the early years empty and the final year overstated. POCM solves this by recognising a share of the contract's revenue and profit each period, in proportion to the work completed. The stage of completion is usually measured by the cost incurred to date against total estimated cost — the cost-to-cost approach.

In India, a construction contractor applies POCM under AS 7, where it is mandatory once the outcome of a contract can be estimated reliably. A real-estate developer not on Ind AS follows the ICAI Guidance Note on Accounting for Real Estate Transactions (Revised 2012), which permits POCM only after project thresholds are met. Developers on Ind AS instead apply Ind AS 115, under which revenue is recognised over time only if strict criteria are satisfied, and otherwise at a point in time on possession.

Key terms

How Percentage of Completion Method (POCM) Works

POCM turns a long contract into period-by-period revenue through a defined path:

  1. 1Estimate total contract cost

    The project accountant and site team build a full budget of costs to complete — the denominator for the whole method.

  2. 2Measure cost incurred to date

    Actual costs booked to the contract at period-end give the numerator; supporting bills and the WIP register are the artefacts.

  3. 3Compute stage of completion

    Cost to date divided by total estimated cost gives the completion percentage for the period.

  4. 4Recognise revenue and cost

    That percentage is applied to contract value to book revenue, with matching cost, in the profit and loss account.

  5. 5Provide for expected losses

    If total cost is expected to exceed contract value, the whole foreseeable loss is booked immediately, not spread.

Where Percentage of Completion Method (POCM) Applies — Construction and Real-Estate Developers

POCM is the natural fit wherever value is delivered gradually over a long build:

  • Multi-year construction contracts — Contractors building roads, plants or towers over two to four years recognise revenue as work proceeds under AS 7.
  • Phased residential projects — Developers releasing a project in phases apply POCM per project once the Guidance Note thresholds are met.
  • Fixed-price infrastructure work — EPC contractors with a fixed price and long timeline use cost-to-cost to smooth revenue.
  • Retention-heavy contracts — Where a portion is retained until defect liability ends, POCM still books revenue as earned, with retention tracked separately.
  • Ind AS developers — Larger listed developers test each contract under Ind AS 115 for over-time versus point-in-time recognition.

How to Calculate Percentage of Completion Method (POCM)

Stage of completion = Cost incurred to date ÷ Total estimated cost; Revenue = Stage × Contract value
InputWhere it comes fromSample value (INR)
Cost incurred to dateContract WIP ledger9,00,00,000
Total estimated costProject budget to complete30,00,00,000
Contract valueSigned contract40,00,00,000
Stage of completionCost to date ÷ total cost30%

Stage = 9 ÷ 30 = 30%. Revenue recognised to date = 30% × ₹40,00,00,000 = ₹12,00,00,000, with ₹9,00,00,000 cost, giving ₹3,00,00,000 profit booked so far.

Percentage of Completion Method (POCM): A Practical Example

ParticularsAmount (INR)Treatment
Contract value (commercial tower)40,00,00,000Total revenue over the build
Total estimated cost30,00,00,000Denominator for completion
Cost incurred by 31 Mar 20269,00,00,00030% complete
Revenue recognised FY 2025–2612,00,00,00030% of contract value
Profit recognised FY 2025–263,00,00,000Revenue less cost to date

A Mumbai contractor building a commercial tower for ₹40 crore has spent ₹9 crore of an estimated ₹30 crore by 31 March 2026. That is 30% complete, so it recognises ₹12 crore of revenue and ₹3 crore of profit in FY 2025–26 — even though the tower is nowhere near handover. If costs later look set to overrun the contract value, the full expected loss must be booked at once, not deferred.

!
Common error

Understating total cost: A low cost estimate inflates the completion percentage and books profit too early → review and revise the cost-to-complete each period.

Common Mistakes With Percentage of Completion Method (POCM)

POCM is only as reliable as the cost estimate behind it:

  • Understating total cost — A low cost estimate inflates the completion percentage and books profit too early → review and revise the cost-to-complete each period.
  • Recognising on cash, not cost — Booking revenue as customer money arrives instead of as work is done breaks the matching principle → measure completion by cost incurred, not collections.
  • Ignoring expected losses — Spreading a foreseeable loss over future periods overstates current profit → provide the entire expected loss immediately under AS 7.
  • Applying POCM below thresholds — A developer booking revenue before the Guidance Note thresholds are met recognises income prematurely → confirm the 25%/25%/10% gates first.
  • Confusing billing with revenue — Treating milestone invoices as revenue mis-states results → revenue follows completion, with billing tracked as WIP or advances.
Quick summary

The Percentage of Completion Method (POCM) recognises revenue and profit on a long project in step with how much of the work is done, rather than only when it finishes. Revenue and costs flow into the profit and loss account each period based on the stage of completion. It matters because it matches income to effort, avoiding lumpy results on multi-year construction and project contracts.

Need help with Percentage of Completion Method (POCM)?

Percentage of Completion Method (POCM) sits inside your day-to-day books. Patron's CA-led team keeps them accurate, compliant and audit-ready.

How is percentage of completion calculated under the cost-to-cost method?

Divide cost incurred to date by the total estimated cost of the contract, then apply that percentage to the contract value. Costs of Rs 6 crore against an estimated Rs 10 crore give 60 per cent completion, so Rs 9 crore of a Rs 15 crore contract is recognised as revenue to date. Any expected loss is booked immediately in full.

What is the difference between the percentage of completion method and the completed contract method?

The percentage of completion method recognises revenue and profit progressively as work is performed, while the completed contract method holds everything back until the contract finishes. Percentage of completion spreads profit across years and is required for construction contracts under AS 7. The completed contract method is no longer permitted for construction contracts in Indian financial statements.

Is the percentage of completion method compulsory for tax in India?

Yes for most contractors. ICDS III on construction contracts requires the percentage of completion method for computing taxable income, and permits revenue recognition to be deferred only while completion stays below 25 per cent. Companies applying Ind AS 115 recognise revenue over time on a similar input measure, so book and tax profiles usually track each other.

Reviewed by the CA & CS Team, Patron Accounting LLP
ICAI & ICSI registered  ·  Reviewed by CA Sundram Gupta (FCA)  ·  Last reviewed 22 Jul 2026  ·  Next review 22 Jan 2027
Official sources: ICAIMCA

Applicable framework: AS 7 (Construction Contracts); ICAI Guidance Note on Real Estate (Revised 2012); Ind AS 115. For general information only, not professional advice. Verify the current position for your entity before acting.