Operational Cost Centres
Definition
An operational cost centre is a unit of a business, such as a department, machine, warehouse or team, to which costs are charged so its spending can be measured and controlled. It incurs cost but does not earn revenue by itself. Cost centres are tracked inside the accounting or costing system; they do not appear on the face of the financial statements.
At a glance
- Category
- Accounting & Bookkeeping
- In this entry
- What it means for Indian businesses How it works · Example
In practice
01 What it means for Indian businesses
Without cost centres, overheads are one company-wide figure that no manager owns. With them, every expense is coded to the unit that caused it, so the business can see where money was spent and who is answerable for it. Tally calls these "cost centres"; other software uses tags, classes or departments for the same purpose.
| Kind of centre | Examples | What happens to its cost |
|---|---|---|
| Operational (production) centre | Machining, assembly, packing | Charged to products, usually on machine or labour hours |
| Service centre | Maintenance, stores, quality control, canteen | Shared out to the operational centres first |
| Profit centre (not a cost centre) | A branch or product line that earns its own revenue | Tracked for profit, not only cost |
Companies in certain industries above set turnover limits must also keep cost records, and cost-centre data feeds them. Under section 148 of the Companies Act 2013, companies in listed industries with overall turnover of ₹35 crore or more in the preceding year must keep cost records; micro and small enterprises are excluded.
How it works
02 How it works
- List the centres
Such as machining, packing, stores and maintenance.
- Code every expense
To a centre when the voucher is entered.
- Share common costs
On a fair, written basis: rent on floor area, power on connected load, supervision on headcount.
- Move service centre costs
Into the operational centres.
- Charge centre costs to products
And compare each centre's actual spend with its budget every month.
Worked example
03 Example
An example, not advice on your facts.
An auto-components maker in Ahmedabad sets up three cost centres.
| Particulars | Amount (₹) | Treatment |
|---|---|---|
| Machining: direct wages and power | 6,40,000 | Machining centre |
| Packing: wages and materials | 2,10,000 | Packing centre |
| Maintenance (service centre) | 1,50,000 | Shared between Machining and Packing |
| Total cost charged to output | 10,00,000 | On machine hours |
Factory rent of ₹6,00,000 for 12,000 sq ft would charge a 3,000 sq ft machine shop ₹1,50,000. When the machining centre's power cost jumps, the monthly report shows it at once instead of at the year end.
Watch out
04 Common mistakes
- Vouchers left without a cost centre, which pile up in "general".
- Sharing common costs on a different basis each month.
- Creating so many small centres that coding becomes a chore.
- Treating a unit that earns revenue as a pure cost centre.
Need help with cost centres? See our MIS Reporting or Chart of Accounts Setup. You can also see our Inventory Accounting and Costing Services.
Review and sources
Sources: ICAI study material ch.10