    A standard cost variance is the difference between what production was expected to cost (the standard cost) and what it actually cost. It is favourable when actual cost is lower than standard and adverse when it is higher. Splitting it into a price part and a usage part shows whether the cause was paying more or using more.

    • Written by Gautami Deshpande, reviewed by CA Puja Pradhan

    Read the full entry

    At a glance

    Category
    Accounting & Bookkeeping
    In this entry
    What it means for Indian manufacturers How it works · Example

    In practice

    01 What it means for Indian manufacturers

    Under standard costing, a business sets a benchmark cost per unit before production: standard material, labour and overhead. Each month, actual consumption and rates are compared with the bill of materials and standard rates. The variances appear in cost records and management reports, not on the face of the financial statements.

    Variances also matter for stock valuation. AS 2 and Ind AS 2 allow inventory to be valued at standard cost only if the result approximates actual cost and the standards are reviewed regularly. Large variances therefore have to be analysed and, at year-end, allocated between closing stock and cost of goods sold.

    Variance Formula Who owns it
    Total cost variance Standard cost of actual output − Actual cost Management
    Material price variance (Standard rate − Actual rate) × Actual quantity Purchasing
    Material usage variance (Standard quantity − Actual quantity) × Standard rate Production

    A negative answer is adverse; a positive answer is favourable.

    How it works

    02 How it works

    1. Set standards

      From the bill of materials and expected rates.

    2. Record actuals

      From purchase invoices, the stock ledger and wage records.

    3. Work out the total variance

      For the actual output.

    4. Split it

      Into price and usage effects.

    5. Act and review

      Send each variance to its owner, and update standards after major price changes.

    Worked example

    03 Example

    An example, not advice on your facts.

    A Chennai fabrication unit makes 1,000 units. The standard is 10 kg of steel per unit at ₹80 per kg. It actually uses 10,300 kg at ₹84 per kg.

    Item Working Amount (₹)
    Standard cost of actual output 1,000 × 10 kg × 80 8,00,000
    Actual cost 10,300 kg × 84 8,65,200
    Price variance (80 − 84) × 10,300 41,200 adverse
    Usage variance (10,000 − 10,300) × 80 24,000 adverse
    Total variance 41,200 + 24,000 65,200 adverse

    Purchasing owns the ₹41,200 from dearer steel; production owns the ₹24,000 from extra wastage. "Costs are up" becomes two specific numbers.

    Watch out

    04 Common mistakes

    • Never revising standards. Out-of-date standards produce meaningless variances.
    • Reporting only the total. Without the price and usage split, nobody knows who should act.
    • Parking variances in suspense. Large unallocated variances misstate stock and cost of sales.
    • Chasing tiny variances. Set a threshold and focus above it.

    Need help with standard costing? See our MIS Reporting Services or Inventory Accounting & Costing. You can also see our Manufacturing Accounting Services.

    Review and sources

    Written by Gautami Deshpande, reviewed by CA Puja Pradhan

    Talk to an expert

    Tell us what you need and the right person calls you back.

    🇮🇳 +91

      By sending this form you agree to our privacy policy.

      Get compliance due-date alerts on WhatsApp. Join →