Glossary · Accounting & Bookkeeping
Bill of Materials (BOM) Costing
Definition
Bill of Materials (BOM) costing builds up the cost of one finished product from its bill of materials. The bill of materials lists every raw material, part and sub-assembly, with the quantity needed for one unit. BOM costing prices each line, then adds direct labour and absorbed overhead. The result is the cost per unit used for pricing, stock valuation and cost control.
At a glance
- Category
- Accounting & Bookkeeping
- In this entry
- What it means for Indian manufacturers How it works · Example
In practice
01 What it means for Indian manufacturers
A bill of materials is the recipe for a product. BOM costing puts a price on every line of that recipe. When a component price or quantity changes, the product cost changes with it.
A manufacturer uses BOM costing when it prices a product, values closing stock or checks how much material production used. The material cost it gives feeds inventory valuation under AS 2 or Ind AS 2 (Inventories). Companies covered by the cost records rules keep product-wise cost records, and a maintained BOM is the base for them.
BOM costing is not the same as standard costing. BOM costing tells you what a unit should cost today at current rates. Standard costing fixes an agreed cost in advance and then explains why actual spending differed from it.
How it works
02 How it works
- Build the BOM
Engineering lists each input and its quantity per unit. A multi-level BOM rolls the cost of each sub-assembly up into the parent item.
- Price each material line
Apply the inventory cost formula (FIFO or weighted average) to each component. Add a scrap allowance where some material is always lost.
- Add direct labour
Cost the labour time per unit at the wage rate.
- Absorb overhead
Charge a share of production overhead on machine or labour hours.
- Value and compare
Use the unit cost to value output and closing stock, and compare it with actual cost to find variances.
The formula is: BOM cost per unit = sum of (component quantity × rate) + direct labour + absorbed overhead.
Worked example
03 Example
An example, not advice on your facts.
A Pune firm makes a small pump.
| Item | Amount (₹) | Treatment |
|---|---|---|
| Steel body: 2 kg at ₹220 | 440 | Material line in the BOM |
| Motor assembly: 1 unit | 200 | Material line in the BOM |
| Direct labour: 0.5 hour at ₹240 | 120 | Conversion cost |
| Absorbed overhead | 90 | Charged on machine hours |
| Cost per finished unit | 850 | Values output and closing stock |
If steel rises to ₹240 a kg, the steel line becomes ₹480 and the pump costs ₹890. For 2,000 pumps, cost moves from ₹17,00,000 to ₹17,80,000. The firm can review its selling price before the margin is lost.
Watch out
04 Common mistakes
- Old component rates. Last year's prices understate cost and overstate margin.
- Wrong quantities. A BOM that does not match real usage hides wastage. Reconcile it with actual consumption.
- Leaving out overhead. Material plus labour alone is below full cost.
- No update after a design change. Tie every BOM revision to an engineering change note.
Questions
05 Questions people ask
- What is BOM costing?
- BOM costing is the method of working out a product's cost from its bill of materials. Each material and part in the list is priced at its quantity per unit, and direct labour and overhead are added. The total is the cost of one finished unit.
- How is BOM cost different from standard cost?
- BOM cost adds up the materials and quantities listed in the bill at their current prices. Standard cost is a planned cost set in advance; comparing the two with actual cost shows where prices or usage have moved.
Need help with BOM costing? See our Inventory Accounting & Costing or Manufacturing Accounting Services.