Glossary · Accounting & Bookkeeping
Work-in-Progress (WIP) Valuation
Definition
Work-in-progress (WIP) valuation is putting a value on goods that are partly made at the end of a period. WIP is valued at the cost built up so far: materials issued, labour spent and a fair share of factory overhead up to the stage reached. It is shown as inventory under current assets. A wrong WIP value misstates both closing stock and the period's profit.
At a glance
- Category
- Accounting & Bookkeeping
- In this entry
- What it means for Indian manufacturers How it works · Example
In practice
01 What it means for Indian manufacturers
At any month-end a factory has goods started but not finished: steel cut but not welded, garments stitched but not packed. WIP sits between raw material and finished goods. An error here flows straight into cost of goods sold and the margin.
Under AS 2 and Ind AS 2 (Inventories), inventory including WIP is carried at the lower of cost and net realisable value. Fixed production overhead is absorbed on normal capacity, not on low actual output. Idle-capacity cost and abnormal wastage are charged to profit and loss, not loaded into WIP. Selling and general administration costs are never part of WIP. A company's balance sheet shows work-in-progress as a separate class of inventories. Schedule III classifies inventories as raw materials, work-in-progress, finished goods, stock-in-trade, stores and spares, loose tools and others, with goods-in-transit under the relevant sub-head.
WIP matters in engineering and auto-component plants, process industries such as chemicals and textiles, job-work units and makers of machinery with long production cycles.
How it works
02 How it works
- List open jobs
Physical checks and the production system show every unfinished job at period-end.
- Assess the stage of completion
Production gives each job a percentage.
- Gather direct costs
Take materials issued and labour booked from stores records and job cards.
- Absorb overhead to that stage
Use normal capacity. Leave out idle and abnormal costs.
- Test against net realisable value
Carry the lower of cost and NRV.
Worked example
03 Example
An example, not advice on your facts.
An Ahmedabad auto-components factory has a batch at the 60% stage at month-end.
| Item | Amount (₹) | Treatment |
|---|---|---|
| Materials issued to the batch | 6,00,000 | In WIP |
| Direct labour booked | 2,50,000 | In WIP |
| Factory overhead to the 60% stage (normal capacity) | 1,50,000 | In WIP |
| WIP cost | 10,00,000 | Carried as inventory (if below NRV) |
| Overhead for idle capacity | 40,000 | Expensed, not in WIP |
Watch out
04 Common mistakes
- Valuing WIP at full cost. Half-made goods are not finished goods.
- Loading idle or abnormal costs into WIP.
- Absorbing overhead on actual output when output is low.
- Ignoring NRV. Write WIP down if its expected realisable value is lower.
Questions
05 Questions people ask
- Is work in progress a current asset?
- Yes. WIP is part of inventories, and inventories are current assets because they are expected to be used or sold within the normal operating cycle. On a company balance sheet it is shown under inventories, separately from raw materials and finished goods.
- What is work-in-progress revenue?
- In service and contract businesses, "WIP" often means work done but not yet billed. The revenue earned on that work is recognised when the work is done, and shown as unbilled revenue until the invoice goes out. See Unbilled Revenue (WIP Hours). In a factory, WIP is valued at cost as inventory, not as revenue.