    Percentage of Completion Method (POCM)

    Definition

    The percentage of completion method (POCM) recognises revenue and profit on a long contract in step with how much of the work is done. It does not wait for the project to finish. Each period, the business books a share of the contract revenue and its matching cost, based on the stage of completion. This keeps multi-year results even instead of showing nothing for years and then one large profit at handover.

    • Written by Gautami Deshpande, reviewed by CA Puja Pradhan

    Read the full entry

    At a glance

    Category
    Accounting & Bookkeeping
    In this entry
    Where it applies in India How it works · Example

    In detail

    01 Where it applies in India

    Business Framework
    Construction contractor (not on Ind AS) AS 7, Construction Contracts: POCM once the outcome of the contract can be estimated reliably
    Company on Ind AS (Rule 4 criteria: listed or listing, other than on an SME exchange; net worth ₹250 crore or more; and their group companies) Ind AS 115: revenue over time only if the over-time criteria are met; otherwise at a point in time, such as on possession
    Income-tax Profits from a construction contract or a service contract are computed on POCM as per ICDS. For tax year 2026-27 onwards this is the corresponding provision of the Income-tax Act 2025. For FY 2025-26 and earlier, the 1961 Act rule applies (section 43CB)

    Under the corresponding provision of the 2025 Act, a service contract of 90 days or less may use the project completion method, and a contract with an indeterminate number of acts over a period uses the straight-line method. The Income-tax Act, 2025 applies from 1 April 2026; for tax year 2025-26 and earlier, the corresponding provision of the Income-tax Act, 1961 applies. Retention money counts as contract revenue, and contract costs are not reduced by incidental interest, dividend or capital gain income.

    How it works

    02 How it works

    1. Estimate total contract cost

      Build the full budget of costs to complete.

    2. Measure cost incurred to date

      Take actual costs booked to the contract at period end.

    3. Work out the stage of completion

      Cost to date ÷ total estimated cost (the cost-to-cost approach).

    4. Book revenue and cost

      Apply that percentage to the contract value.

    5. Provide for losses at once

      If total cost is expected to exceed the contract value, book the whole expected loss immediately.

    The older completed contract method, which holds back all profit until the contract ends, is not used for construction contracts under AS 7 (Revised 2002), which requires the percentage of completion method.

    Worked example

    03 Example

    An example, not advice on your facts.

    A contractor signs a ₹40 crore contract for a commercial tower. The estimated total cost is ₹30 crore. By 31 March 2026 it has spent ₹9 crore.

    Item Amount (₹) Working
    Stage of completion 30% 9 ÷ 30
    Revenue recognised to date 12,00,00,000 30% × 40,00,00,000
    Cost recognised to date 9,00,00,000 Actual cost
    Profit recognised to date 3,00,00,000 12 crore − 9 crore

    If the cost estimate later rises above ₹40 crore, the full expected loss is booked in that period.

    Watch out

    04 Common mistakes

    • Understating total cost. A low estimate inflates the completion percentage and books profit too early. Revise the cost to complete every period.
    • Booking revenue on cash received. Completion follows cost incurred, not collections.
    • Treating milestone invoices as revenue. Billing is tracked separately as receivable or advance.
    • Spreading a foreseeable loss over later years. The whole loss is booked at once.
    • Using POCM for a real-estate project before the Guidance Note thresholds are met.

    Questions

    05 Questions people ask

    What is the percentage of completion method for revenue recognition?
    It is a way of recognising revenue on a long contract as work progresses. The stage of completion, usually cost to date over total estimated cost, is applied to the contract value to find the revenue for each period.
    Is the percentage of completion method still allowed?
    Yes. In India, AS 7 requires it for construction contracts once the outcome can be estimated reliably, and the corresponding provision of the Income-tax Act 2025 requires it for tax on construction and most service contracts. Companies on Ind AS apply Ind AS 115, which recognises revenue over time only when its criteria are met.

    Need help with the percentage of completion method? See our Construction & Real Estate Accounting or Service Sector Accounting.

    Review and sources

    Written by Gautami Deshpande, reviewed by CA Puja Pradhan

    Sources: Income-tax Act, 2025; ICAI: Ind AS 115 Revenue from Contracts with Customers; AS 7 Construction Contracts: official copy 1, official copy 2