    Capital Work-in-Progress (CWIP)

    noun · abbreviated CWIP

    Definition

    Capital work-in-progress (CWIP) is the cost spent on an asset that is still being built or installed and is not yet ready for its intended use. The cost is collected project by project in a separate CWIP balance. When the asset is ready for use, the cost moves out of CWIP into property, plant and equipment, and only then does depreciation begin.

    • Reviewed by CA Sundram Gupta · Chartered Accountant
    • Last reviewed 23 October 2026
    • 8 min read

    See related terms

    At a glance

    Full form
    Capital work-in-progress Cost of assets still being built or installed
    Leaves CWIP
    When the asset is ready for use Not when the last bill arrives
    Depreciation
    None while the cost waits It starts once the asset is available for use
    Shown with
    An ageing in four bands For companies, under amended Schedule III
    Checked on site
    Progress against cost booked The oldest projects get the closest look

    Meaning

    01 What capital work-in-progress is

    Building a factory shed or installing an imported machine takes months, and money goes out long before anything can be used. Those payments are not running costs, because they buy something the business will keep. They cannot sit with finished assets either, because nothing is working yet. CWIP is the waiting room in between: a balance that holds the cost until the asset is ready to do its job.

    Two things keep CWIP honest. Every cost in it must belong to a project that is genuinely still under way, and the day an asset can work as intended, its cost must leave. Verifications find problems on both sides: balances that keep growing while nothing changes on site, usually from advances, wrong postings or a project that quietly stopped, and finished assets that are running but were never moved out.

    On the register

    02 How CWIP sits beside the fixed asset register

    CWIP is tracked by project, not by asset. The register takes over once something is finished.

    While the work is under way

    • A project reference, not a tag. There is nothing finished to label or locate, so costs are collected against the project.
    • No life and no charge. No useful life or depreciation rate is attached while the cost waits in CWIP.
    • A start date for each project. The age of each project feeds the ageing bands in the accounts.

    Once the asset is ready for use

    • The cost moves across. The project balance is transferred and closed, not left with an unexplained remainder.
    • New register lines open. Each finished asset gets its own number, location, custodian and useful life.
    • Parts are split here. Where a part has a different life from the rest, it gets its own line at this point.
    The handover is the control point. A project that is finished on the floor but still open in CWIP is one of the first things a verification looks for.

    In practice

    03 How CWIP works in practice

    Costs to dateMoved outCWIP balance
    Input Where it comes from Sample (INR)
    Costs to date Every bill booked to the project since it started 2,10,00,000
    Moved out Parts of the project already ready for use and transferred 65,00,000
    CWIP balance What is still waiting, project by project 1,45,00,000

    2,10,00,000 − 65,00,000 = ₹1,45,00,000. Sample figures for illustration only.

    A project from approval to handover

    1. Approve the project and open a CWIP account

      One account for each project, so costs and start dates stay separate from day one.

    2. Book the costs of getting the asset ready

      Building work, equipment, delivery, installation and the cost of testing whether it works properly. Staff training is not part of the asset’s cost.

    3. Track the age of every project

      Companies need it to show the CWIP ageing in their financial statements.

    4. Move the cost out when the asset is ready for use

      Readiness sets the date, not the final invoice or a contractor’s sign-off; depreciation runs from then.

    5. Deal with stalled or abandoned projects

      A project that has stopped is reviewed and its cost dealt with, rather than carried forward unchanged. Once a project is abandoned no benefit is expected from it, so its cost is taken out of CWIP (AS 10 paragraph 74(b); Ind AS 16 paragraph 67(b)): any amount recoverable by selling the materials or equipment can stay on the books and the rest goes to profit or loss. A project that is only paused or doubtful is tested for impairment instead and shown separately in the CWIP ageing note.

    Worked example

    04 A CWIP schedule at the year end

    Four projects, one in each ageing band, and what a verifier asks of each.

    Sample CWIP schedule for a manufacturer with four open projects
    Project Ageing band What the verifier checks
    New packing line Less than 1 year Installation stage seen on site
    Warehouse extension 1 to 2 years Building work matches the cost booked
    Office floor fit-out 2 to 3 years Whether the floor is already occupied and in use
    Effluent treatment plant, on hold More than 3 years Whether work has stopped; overdue, so a completion schedule is needed

    The oldest bands are where the questions are

    The packing line is still being installed, so it rightly stays in CWIP. The office fit-out is the line to test: if staff have worked on that floor for months, it was ready for use then and should already have left CWIP, with depreciation running from that date.

    The effluent plant has sat in the oldest band with no work on site. For a company, an overdue project needs its own completion schedule in the accounts, and the verifier records what is physically there against the cost still carried.

    Framework

    05 Capital work-in-progress under Indian rules

    For companies, Schedule III to the Companies Act, 2013 sets how CWIP is presented. Its amendment by MCA notification of 24 March 2021, applying from 1 April 2021, requires CWIP to be shown with an ageing in four bands: less than one year, one to two years, two to three years and more than three years. Projects that are overdue, or have gone over their original cost, need a completion schedule. The accounting standards add that depreciation begins only when an asset is available for use, which is why cost still in CWIP is not depreciated.

    Verified

    Ageing and completion schedule

    CWIP is aged in four bands, and each project that is overdue or over its original cost gets a completion schedule.

    The amendment on MCA
    Verified

    No depreciation before use

    Depreciation starts when the asset is in the location and condition to work as intended (AS 10 para 57; Ind AS 16 para 55).

    AS 10 on ICAI
    Verified

    Where CWIP sits in the balance sheet

    CWIP is reported apart from finished property, plant and equipment. Under Schedule III to the Companies Act, 2013, a company following Accounting Standards shows it under non-current assets within 'Property, Plant and Equipment and Intangible assets', after intangible assets, while an Ind AS company shows it as its own line straight after property, plant and equipment. Since FY 2021-22 the notes must also give a CWIP ageing schedule (less than 1 year, 1-2 years, 2-3 years, more than 3 years), split between projects in progress and projects temporarily suspended.

    Watch out

    06 Common mistakes with CWIP

    Most CWIP errors are about timing: cost that leaves too late, or never leaves.

    Leaving a working asset in CWIP

    No depreciation has been charged since it came into use.

    Transfer it from the date it was ready for use.

    Waiting for the final bill

    The handover date follows the paperwork, not readiness.

    Use the date the asset could first work as intended.

    A balance that grows with no progress

    Advances, wrong postings or a stalled project hide inside it.

    Match each project’s cost to what is physically on site.

    One CWIP total for every project

    The four-band ageing cannot be prepared from it.

    Keep a separate account and start date for each project.

    Carrying an abandoned project

    Cost stays on the balance sheet for something that will never be used.

    Review stopped projects and decide their treatment.

    Training booked into the project

    A cost that does not belong to the asset inflates it.

    Keep staff training out of the project cost.

    Questions

    07 Capital work-in-progress FAQ

    What does capital work mean?

    In this phrase, capital work is construction or installation work on an asset the business will keep and use, such as a building or a machine, rather than on goods it will sell. While that work is unfinished, its cost is shown as capital work-in-progress; once the asset is ready for use, it becomes a fixed asset.

    How to account for capital work in progress?

    Book each cost of building or installing the asset to a CWIP account for that project, keeping projects apart so their age can be shown. Include what is needed to get the asset working, such as installation and testing, but not staff training. When the asset is ready for its intended use, transfer the total to fixed assets and start depreciation.

    Do we depreciate capital work in progress?

    No. Depreciation starts when an asset is available for use, that is, when it is in the location and condition needed to work as intended. An asset still being built or installed has not reached that point, so its cost in CWIP is not depreciated.

    CA Sundram Gupta

    Reviewed by CA Sundram Gupta · Chartered Accountant

    Patron Accounting LLP. Regulatory statements on this page (Schedule III; AS 10 and Ind AS 16) signed off by CA Sundram Gupta: 23 October 2026

    Last reviewed: 23 October 2026 Applies to: businesses building or installing assets for their own use; the Schedule III points to companies

    Sources: Schedule III to the Companies Act, 2013, as amended on 24 March 2021 (MCA); AS 10, Property, Plant and Equipment, paras 18, 20 and 57 (ICAI). General information, not professional advice; check the current position for your entity before acting.

    Need help with capital work-in-progress? See our fixed asset verification service. A verification checks each CWIP project against what is on site.

    Talk to an expert

    Tell us what you need and the right person calls you back.

    🇮🇳 +91

      By sending this form you agree to our privacy policy.